Construction risk beyond the budget: What project data tells us - by Lucas Giacalone
A construction budget can appear sound while a project’s risk profile is changing. Material purchases may remain outstanding, site conditions may require additional work, or the schedule may be slipping without a corresponding adjustment to projected costs. For lenders, owners and developers, understanding those relationships is essential to evaluating whether a project remains on track.
National pricing trends provide useful context; The Associated General Contractors of America reported that input prices for new nonresidential construction rose 8.9% between August 2025 and August 2026. That increase places pressure on project budgets, although its effect varies with building type, material requirements and purchasing decisions. An industry index helps describe the environment, but evaluating an individual project requires a closer review of its scope and execution.
Data compiled through KOW’s proprietary reporting software provides another perspective, connecting preconstruction cost information with observations made during construction. These project specific data points help identify where a broad market trend may warrant closer attention, and where an apparent improvement deserves further investigation.
Consider construction costs per square foot. Across the preconstruction projects KOW reviewed in Q4 2026, the weighted average was $224 per gross s/f (excluding data centers) compared with $263 in the second quarter of 2026. That represents a decrease of 14.7%. Taken alone, the comparison could suggest that construction pricing had eased considerably.
The residential cost-per-unit figures moved in the opposite direction. Through October 31, 2026, the weighted average reached $271,524 per unit, an increase of 5.9% from $256,276 in the second quarter of 2026.
These results illustrate an important limitation of aggregate benchmarks. The projects being evaluated can change between periods, bringing different locations, building types, unit sizes and specifications into the calculation. A lower average cost per s/f does not mean that an equivalent building can now be constructed for less.
For a lender or developer evaluating a proposed budget, the practical question is how closely the benchmark resembles the actual project. Comparisons become more useful when the team understands what the cost includes, how the area is used, and whether the underlying scope is comparable.
Analyzing trade allocations as a percentage of the total budget can help when reviewing a budget’s feasibility. Within the residential projects reviewed, site construction represented the largest trade allocation, accounting for 16.3% of total trade costs. That share highlights the importance of understanding site requirements early.
Earthwork, utilities, drainage and related improvements require coordination among the design documents, supporting investigations and contractor’s scope. Where those elements remain unresolved, a seemingly complete budget may still contain substantial uncertainty. Reviewing the allowances and exclusions associated with site work can be as consequential as reviewing the overall construction total.
During construction, schedule performance adds another dimension. Among the projects KOW monitors within this study, 59.3% were on or ahead of schedule. For delayed projects, the median delay was 57 days.
Additional time can affect carrying costs, occupancy plans and the timing of revenue. Evaluating schedule performance therefore requires more than recording a revised completion date. The team needs to understand which activities are driving the delay, what work depends on them (what is the critical path?) and whether the proposed recovery measures are achievable.
Weather accounted for 27.0% of recorded delays, making it the leading reported cause. Although weather cannot be controlled, its potential effect should inform seasonal sequencing and the planning of exposed activities. Once time has been lost, recovery assumptions need to reflect the remaining work and actual field conditions.
Change orders offer a similar lesson about looking beneath a headline figure. Average net change orders across the projects analyzed equaled 1.7% of the original contract amount. However, 11.1% of projects experienced contract growth of at least 5%.
A modest average can coexist with meaningful exposure on individual jobs. Reviewing that exposure means examining the cause of each change, the status of unresolved items and the contingency available for the remaining scope. The approved change order total is one part of that assessment.
For lenders, owners and developers, the strongest use of construction data is to support timely questions and informed action. Cost benchmarks can reveal assumptions that need testing. Trade allocations can identify scopes requiring closer review. Schedule and change order information can show where execution is departing from the original plan.
Bringing these observations together creates a clearer view of a project’s position. That visibility helps teams address emerging issues while there is still time to adjust procurement, sequencing, scope or funding and gives decision-makers a firmer basis for evaluating the work ahead.
Lucas Giacalone is director of technology & compliance at KOW Building Consultants, Manhattan, N.Y.