Laquila and WNW pour concrete for Forest City's Atlantic Yards project
According to Forest City Ratner Companies, the developer of the Atlantic Yards project, The Laquila Group, an excavation and foundation contractor, along with WNW Concrete Contracting, a local minority owned business, has begun pouring concrete for the foundation of the Barclays Center.
Nearly 700 cubic yards of concrete from two plants, delivered in 80 concrete mixing trucks, has been poured in the first two foundation footings.
"We're thrilled that we are fully in the construction phase," said Bob Sanna, the executive VP in charge of construction at FCRC. "Over the next few months we will continue with the mass excavation, underground plumbing and electrical work along with ongoing foundation work."
Sanna said that approximately 13,000 cubic yards of concrete will be used in the Barclays Center foundation. He expects 6,565 tons of steel to be used to construct the arena and an additional 2,693 tons for the arena roof.
This special section will feature projects completed within the past six months as well as projects that are currently under construction across Long Island, submitted by developers, general contractors, construction managers, and architectural firms.
Merritt Environmental Consulting Corp. (MECC) was established in June of 2009 after being part of a larger engineering firm for almost 20 years. The focus of the company is to assist lending institutions, attorneys, real estate investors, and property owners with environmental concerns. Today, MECC has offices in New York, Florida, and Vermont and has grown into a regional consulting firm serving clients along the East Coast.
Adaptive reuse has become one of the most important conversations in commercial real estate today. Long Island has a large inventory of aging retail, office and industrial
The Long Island Board of Realtors (LIBOR) Commercial Network continues to play a key role in advancing opportunities and strengthening the commercial real estate landscape across Queens. Through targeted programming and global outreach
Many attorneys operating within the construction space are familiar with the provisions of New York Lien Law, which allow for the discharge of a Mechanic’s Lien in the event the lienor does not commence an action to enforce following the service of a “Section 59 Demand”.